Installation of the lift shaft formwork system in progress.

Lei Tung Station - Entrance "B" Shaft
Ap Lei Chau, Hong Kong

Entrance shaft to the underground station.

  • Concrete lining to the escalated shaft
  • 4 No. lift shafts
  • Total Height: 52.47 m
  • Total Depth: 40.60 m
  • Shaft above ground: 11.87 m high, 4 storey structure

Construction period: March - September 2015

 

 

Location
Project participants
Customer: Leighton - John Holland JV

The Project

Impressions from the project process
1 /
2
Installation of the lift shaft formwork system in progress.
Installation of the lift shaft formwork system in progress.
Installation of the lift shaft formwork system in progress.

Project Information

Requirements
Fast, reliable and trouble-free operation
All platforms able to be hydraulically climbed
Maximum safety for workers
Additional rebar fixing level required on all platforms
Ability to complete the tight 7 month programme
Simple, efficient stocking procedure for lift shaft internal forms

show more
Solutions
RCS-Lss (Lss = Lite single sided)
RCS-T (T = Tower)
Vario GT 24

Customer benefits
Easy to use with, no skilled labour required
Capable of self-climbing, if required
Fast and reliable
Able to meet the tight programme requirements of 7 months to complete
Technical supervisor to ensure fast and reliable start-up

show more

Related Products

Want to know how PERI can support your project?

We will tailor the most optimal solution to meet your specific requirements.

Installation of the lift shaft formwork system in progress.
Installation of the lift shaft formwork system in progress.

Ap Lei Chau Hong Kong

Calculate route
Installation of the lift shaft formwork system in progress.
Installation of the lift shaft formwork system in progress.